Ansys Learning Forum › Forums › Discuss Simulation › LS Dyna › control termination end-time in LSDyna › Reply To: control termination end-time in LSDyna
December 6, 2023 at 2:33 pm
Ansys Employee
Hi Imran,
You can check the results while the simulation is on-going to verify that they are in line with your expectation.
Make sure that you have requested sufficient intermediate points to be recorded using *Database cards (check Page 1829 of the LS-DYNA manual: https://www.dynasupport.com/manuals/ls-dyna-manuals/ls-dyna_manual_volume_i_r13.pdf). For example, if your simulation takes 5 seconds, you can request to output data at every 0.1 s. Once the output files are generated during the simulation, you can open them using LS-PrePost.