Ansys Learning Forum Forums Discuss Simulation General Mechanical Parametric Study updates entire workbench project, how to prevent it ? Reply To: Parametric Study updates entire workbench project, how to prevent it ?

Ashish Khemka
Forum Moderator

Hi,

Try selelcting the requireried analysis system and then click on update. For example you have 5 analysis systems (A to E) and you want to update just 3 of them then select one and ctrl and select the remaining two and then hit on update button.

Regards,

Ashish Khemka